Heating Project Update - Trenches in the Choir Pews

The pipework is now all connected and pressure tested. It should be filled on Friday and tested next week. The church has been emptying of the plumbers’ equipment all this week.  The vicars stalls are back in place at the front of the chancel. The heat trenches in the choir pews are temporarily covered until new grating arrives, though you can see one piece. 
While the church is clear, they’ve been replacing all the light bulbs at height, and checking the clerestory windows (the clerestory is the top level in the nave). 
Outside the north door broken flagstones have been replaced or relaid. 
Providing the heating tests go well next week, we are on course for handover during the week after Easter, and back into the church at the beginning of June once everything is cleaned and put back in place.